Second new Georgia reactor begins splitting atoms in key step to making electricity

A nuclear power plant in Georgia has begun splitting atoms in the second of its two new reactors, in a key step toward providing carbon-free electricity

By JEFF AMY
Published - Feb 14, 2024, 10:51 AM ET
Last Updated - Feb 14, 2024, 10:51 AM EST

ATLANTA (AP) — A nuclear power plant in Georgia has begun splitting atoms in the second of its two new reactors, Georgia Power said Wednesday, a key step toward providing carbon-free electricity.

The unit of Atlanta-based Southern Co. said operators reached self-sustaining nuclear fission inside the reactor at Plant Vogtle, southeast of Augusta. That makes the heat that will be used to produce steam and spin turbines to generate electricity.

Plant Vogtle’s Unit 4 is now supposed to start commercial operation sometime in the second quarter of 2024, or between April 1 and June 30. The utility earlier this month announced a delay past an earlier deadline of March 30 because of vibrations found in a cooling system.

Georgia Power said it is continuing with startup testing on Unit 4, making sure the reactor’s systems can operate at the intense heat and pressure inside a nuclear reactor. Georgia Power says operators will raise power and sync up its generator to the electric grid, beginning to produce electricity. Then operators will seek to gradually raise the reactor’s power to 100%.

Our Offices
  • 10kInfo, Inc.
    13555 SE 36th St
    Bellevue, WA 98006
  • 10kInfo Data Solutions, Pvt Ltd.
    Claywork Create
    11 km, Arakere Bannerghatta Rd, Omkar Nagar, Arekere,
    Bengaluru, Karnataka 560076
4.2 12182024